Fence construction work in Kirène
Our team had to carry out the closing work of a 6000m2 site in Kirène with the company China engineering Group. The work consisted of installing a Zinc fence with IPNs of 80 along the perimeter of the site. To do this, we were accompanied by our team of topographic surveyors for the implementation of the IPN as well as our civil engineering engineers and our metal welders for the welding part, our painters for the anti-rust paint part and our maneuvers. We also built a small box for the site guard, a road barrier and a 3.5m sliding door that allows access to vehicles and staff. The work lasted only 15 days.