Installation and assembly work of a tower crane in Dakar at the Gueule Tappé market

Installation and assembly work of a tower crane in Dakar at the Gueule Tappé market

Diallo BTP carried out the installation and assembly work of a tower crane in Dakar more precisely at the Gueule Tapée market for a French company called kerely_Building. To do this, we made a foundation with a depth of 2 m with marine cement during pouring in order to curb the corrosion of the iron due to an excessive presence of water (groundwater) on the site. To set up the crane, we used our 20-ton mobile crane truck and all the work took us only 15 days.